ANALISIS NILAI HASIL TERHADAP WAKTU MENGGUNAKAN SOFTWARE MICROSOFT PROJECT (STUDI KASUS PADA PROYEK PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR KPU KABUPATEN MAJALENGKA)

Indonesia

Authors

  • Arief Rijaluddin Universitas Majalengka
  • Awit Wijayanti Universitas Majalengka

DOI:

https://doi.org/10.31949/jensitec.v10i01.7344

Abstract

The rapid of economic growth in Indonesia, of course, accompanied by the increasing public demand for construction projects. Each project has a different goal, in the implementation of the General Election Commission Office Building Construction Project which is planned for 143 calendar days, namely in the period 10th August 2020 to 31st December 2020 by the Contractor PT. Kalimasada Zahraa Jaya with a project value of Rp. 4.306.705.600,- 

In the process of achieving these goals, a good construction management is needed so that the project is in accordance with the plan. In this case, the Earned Value Analysis method is used to determine if there is a discrepancy in the implementation of the project. The data analysis process uses Microsoft Project software for project scheduling and human resource allocation for each element of work effectively and efficiently. The data analyzed include presenting S curve graph data, calculating the schedule variance "SV" and SPI values from the BCWP and BCWS data values every week or cumulatively to produce the actual project duration and the remaining total duration.

From the results of the "EVA" method in the 20th week, the comulative EV value of Rp. 4,306,705,600,

which shows that the costs incurred to complete the project are in accordance to the plan. The resulting SV figure is + Rp 20,499,919,- which means that the completion of the work is faster than the plan and the SPI value is 1,005, the project implementation performance is better than the schedule planning ahead of the plan.

Keywords:

Construction Project, Earned Value Analysis, Microsoft Project, S Curve

Downloads

Download data is not yet available.

References

Anonim. 2004. A Guide To The Project Management Body Of Knowledge Project Management Institute 3rd edition. Pennsyvalnea : USA.

Cahyadi, E.R. 2001. A Guide to the Project Management Of Body Knowledge (PMBOK Guide). USA : Project Managent Institute.

Clough, Richard H and Sears, Glenn A. 1991. Construction Project Management. Canada : John Willey & Sons Inc.

Dipohusodo, Istimawan. 1996. “Manajemen Proyek & Konstruksi Jilid 1”. Yogyakarta: Kanisius

Ervianto, Wulfram. 2002. “Manajemen Proyek Konstruksi”, Yogyakarta : Penerbit Andi.

Ervianto, Wulfram. 2004. “Teori Aplikasi Manajemen Proyek Konstruksi Edisi 1”, Yogyakarta.

Eddy Herjanto, 2001,” Manajemen Produksi dan Operasi Edisi Ke Dua”. Jakarta : PT. Gramedia.

Filastri. 2015. “Analisa Biaya Dan Waktu Proyek Pembangunan Kampus Politeknik Menggunakan Konsep Nilai Hasil/ EVM”. Teknik Sipil Makassar.

Heizer, Jay dan Barry Render. 2008. Operation Management, 9th Edition. USA : Pearson Prentice Hall.

https://123dok.com/document/z1dmr93z- analisis-nilai-proyek-konstruksi-proyek- pembangunan-eastparc-yogyakarta.html

https://ejournal.unsrat.ac.id/index.php/jss/ar ticle/view/2497 https://www.slideshare.net/ichottt28/micros oft-project-44346850

Husen, Abrar. 2008. “Manajemen Proyek”. Yogyakarta : Penerbit Andi.

Kerzner, H. 1995. Project Management. New York : Van Nostrand Reinhold Company.

Mahadewi, A.A.S.A. 2006. “Evaluasi Proyek Dengan Konsep Nilai Hasil (Earned Value) Pada Proyek Pembangunan Gedung Instalasi Rehabilitasi Medik Rs Sanglah Denpasar”. Skripsi Teknik Sipil Unud.

Project Management Institute. 1996. A Guide To The Project Management Body Of Knowledge (PMBOK). United States : PMI Publications.

Radjatadoe, S. Farmy. 2012. “Penjadwalan Proyek”. Yogyakarta : Penerbit Andi.

Sudarsana, Dewa Ketut. 2008. “Pengendalian Biaya Dan Jadual Terpadu Pada Proyek Konstruksi”. Jurnal Ilmiah Teknik Sipil. Winoto, D.Y Agnes. 2014. “Manajemen Konstruksi Untuk Bangunan”.

Yogyakarta: PT. Taka Publisher.

Downloads

Abstract Views : 150
Downloads Count: 79

Published

2023-12-08

How to Cite

Rijaluddin, A., & Awit Wijayanti. (2023). ANALISIS NILAI HASIL TERHADAP WAKTU MENGGUNAKAN SOFTWARE MICROSOFT PROJECT (STUDI KASUS PADA PROYEK PEMBANGUNAN KONSTRUKSI GEDUNG KANTOR KPU KABUPATEN MAJALENGKA): Indonesia. J-ENSITEC, 10(01), 904–914. https://doi.org/10.31949/jensitec.v10i01.7344

Similar Articles

<< < 1 2 3 > >> 

You may also start an advanced similarity search for this article.