STUDI EVALUASI PENGENDALIAN BIAYA (COST CONTROL) DAN JADWAL PELAKSANAAN (SCHEDULING) PADA PROYEK PEMBANGUNAN GEDUNG RAWAT JALAN DAN BASSEMENT RSUD MAJALENGKA MENGGUNAKAN METODE EARNED VALUE DAN SOFTWARE MS. PROJECT
Indonesia
DOI:
https://doi.org/10.31949/jensitec.v8i01.1910Abstract
Planning and controlling costs and time is part of the overall construction project management. In addition to the assessment in terms of quality, the achievement of a project can also be assessed in terms of cost and time. The costs that have been incurred and the time spent in completing a job must be measured continuously for deviations from the plan. The presence of significant cost and time deviations indicates poor project management. With the existence of project performance indicators in terms of cost and time this allows preventive actions so that project implementation goes according to plan. The concept of "Earned Value" is one of the tools used in project management that integrates cost and time and by using Ms. Projects. Ms. Project is a project management software product and is developed and sold by Microsoft. It is designed to assist a project manager in developing plans, assigning resources and tasks, tracking progress, managing budgets and analyzing workloads. From the results of the evaluation of cost control and project schedules on outpatient and basement building construction projects using the earned value method, it can be concluded that the CV (Cost Variant) in this project results in 0 which means the Zero Number on the Cost Variant indicates that the cost is within the budget, SV (Schedule). Variant ) the value shows a negative number, this means that the completion of the work is delayed, the CPI (Cost Performance Index) is 1, meaning that the expenditure is in accordance with the project budget
Keywords:
Result Value Concept, BCWP, BCWS, ACWP, Ms. ProjectDownloads
References
2. Cioffi, D. F., 2005. A Scientific Notation And An Improved Formalism For Earned Value Calculations, Skripsi, United States
3. Ervianto, W. I., 2004. Teori-Aplikasi Manajemen Proyek Konstruksi, Andi, Yogyakarta
4. Ervianto, W. I. ,2005. Manajemen Proyek Konstruksi, Andi, Yogyakarta
5. Frailey, D. J., 1999. Tutorial on Earned Value Management Systems, Jurnal
6. Henderson, Kym., 2007. A Breakthrough Extension to Earned Value Management, skripsi, Sydney Australia
7. http://puslit.petra.ac.id/journals
/civilengineering/. Diakses Oktober 2009
8. Luthan, P. L. A., dan Syafriandi. 2005. Aplikasi Microsoft Project Untuk Penjadwalan Kerja Proyek Teknik Sipil, Andi, Yogyakarta
9. PMI, 2005, Practice Standard for Earned Value Management, PMI, Pennysilvania
10. Irfanur , Rahman., 2010. Earned Value Analysis terhadap biaya proyek pembangunan gedung, Jurnal Tugas Akhir, Universitas Sebelas Maret Surakarta
11. Sudarsana, D. K., 2008. Pengendalian Biaya Dan Jadual Terpadu Pada Proyekkonstruksi, Jurnal Ilmiah, Universitas Udayana
12. Wilkens, T. T., 1999. Earned Value Clear and Simple, Jurnal, United States
Published
How to Cite
Issue
Section
License
An author who publishes in the J-ENSITEC (Journal of Engineering and Sustainable Technology) agrees to the following terms:
- Author retains the copyright and grants the journal the right of first publication of the work simultaneously licensed under the Creative Commons Attribution-ShareAlike 4.0 License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal
- The author is able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book) with the acknowledgment of its initial publication in this journal.
- The author is permitted and encouraged to post his/her work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of the published work